Building Update – December 1, 2023

Completion Countdown: 30 days!

CHECKLIST:

Design and Permitting – 100%

Planning and Acquisition – 100%

Demolition – 100%

Major Construction – 75%

Exterior Improvements:

Playground Prep – 95%
Basketball Court – 25%
Playground Equipment – 20%

Interior Improvements:

Wall Finishing & Painting – 85%
Ceiling Finishes – 90%
Bathroom Tiles – 75%
Rooms and Hallways Flooring – 20%

Remodel expected to be complete by Jan 2024 B’ezras Hashem!!