As of today, we have completed:
- New Roof
- second floor advancements include drywall, plumbing, and HVAC finalizations
- Classrooms now have backing for interactive displays
- Technology (servers/wifi/APs) is set, funded by a government grant. Kohost.AI ensured optimal safety
- Orders placed for millwork, furniture, and window shades.
- Upcoming: Ceiling grid installations, lighting, and HVAC vents.
From the desk of the Chairman of the YDLV Acquisition and Development Committee Jonathan Baktari MD, CEO of www.usdrugtestcenters.com www.enationaltesting.com www.e7health.com jonathanbaktarimd.com