Categories
Building Updates

Building Update – Sept 15, 2023

Our construction team has been working hard to make progress on the building. Here are some of the updates for this week:

  • First Floor: The electric wiring rough-in is complete and data and low voltage are being installed.
  • Second Floor: Framing is 50% done.
  • Outside: Water and sewer work continues. On a given day, there are over 40 workers on site!

We are pleased with the progress that has been made so far and we are looking forward to seeing the building come together. We will continue to keep you updated on the progress of the construction.

Thank you for your continued support!

From the desk of the Chairman of the YDLV Acquisition and Development Committee Jonathan Baktari MD, CEO of www.usdrugtestcenters.com www.enationaltesting.com www.e7health.com jonathanbaktarimd.com